West Yorkshire plastics manufacturer

Their insurer asked for an upgraded fire alarm. A local firm had turned the job down as too complex.

Manufacturing & engineering Fire alarms

Points installed, including an aspirating system
159
Approximate timescale
8 weeks
Industrial unit with silver cladding, a red brick base and blue roller shutter doors

The upgrade was needed to meet new regulations, and the job was referred to us because we specialise in commercial properties.

After the first site survey, the customer had a full price within three days, and the installation started four weeks later.